The 10-Point RTU Replacement Bid Checklist
The scope and equipment checks that catch missing items before you sign a replacement contract. Print it, or run through it on your next set of bids.
1. Unit selection matches the existing installation
Tonnage, voltage, gas/electric configuration, and footprint verified against the unit being replaced — not assumed.
2. Curb and curb adapter are in the scope
A mismatched curb discovered on crane day is the most expensive surprise in a replacement project.
3. Crane, rigging, and old-unit disposal included
Confirm who pays for the crane, street permits, and legal disposal of the old equipment and refrigerant.
4. Efficiency ratings compared on operating cost
SEER2/IEER differences between bids translate to real utility dollars over a 15–20 year life. Compare them.
5. Warranty terms spelled out
Parts vs. labor, compressor and heat exchanger terms, and who registers the warranty — get it in writing.
6. Controls and thermostat integration defined
Confirm the new unit connects to your existing controls or thermostat — and who does that work.
7. Electrical and gas reconnection scope defined
Disconnects, whips, gas piping modifications — missing here means a change order later.
8. Code-required items priced in
Smoke detectors, economizers, permits, and current code requirements included — not excluded in fine print.
9. Startup, testing, and documentation included
Factory startup, test & balance, and closeout documentation should be part of the price.
10. Bids are line-itemized and comparable
If you can't compare the bids line by line, you can't know which one is actually the best value.
Want MSC to run this review on your bids?
Independent bid review catches scope gaps on paper — before they become change orders on your roof.